NEW QUESTION 49
Which statement is valid regarding networks?
- A. A network activity can be assigned to several WBS elements
- B. Relationships can be used to connect activities of different networks
- C. Material components can be assigned to activity elements
- D. A network can be activity-account-assigned and header-account-assigned
Answer: A
NEW QUESTION 50
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. BOM item
- B. WBS element
- C. Material master
- D. Network activity
Answer: A,D
NEW QUESTION 51
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Controlling area
- B. Company code
- C. Operating concern
- D. Sales organization
- E. Plant
Answer: A,B,E
NEW QUESTION 52
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.
- A. Automatic activation with budget assignment
- B. Background activation (CJBV - Activate Availability Control)
- C. Automatic activation with the first actual posting
- D. Automatic activation with assignment to an investment program
Answer: A,B
NEW QUESTION 53
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing authorizations to release material components
- B. Missing material availability
- C. Missing budget for material components
- D. Missing reservations for material components
Answer: A
NEW QUESTION 54
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?
- A. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- D. Set up the requirement date aligned with the activity start date and an offset of 5 days
Answer: A
NEW QUESTION 55
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The MRP controller for the network
- B. The person responsible for the work center
- C. The person responsible for the superior WBS element
- D. The person responsible for the network activity
Answer: A
NEW QUESTION 56
Dates
How are earliest dates and latest dates of activities schedule?
- A. Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.
- B. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
- C. Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.
- D. Earliest dates and latest dates are scheduled by forward scheduling.
Answer: B
NEW QUESTION 57
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Item category
- B. Control key
- C. Requirement class
- D. Project profile
Answer: D
NEW QUESTION 58
The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false.
- A. False
- B. True
Answer: A
NEW QUESTION 59
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. WBS elements
- B. Project definition
- C. Milestones
- D. Sales order items
Answer: A,D
NEW QUESTION 60
COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?
- A. Availability control
- B. Cost forecast
- C. Easy cost planning
- D. Results analysis
Answer: A
NEW QUESTION 61
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. The system automatically creates a new purchase requisition with the difference to the original quantity
- B. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
- C. The purchase order is updated automatically to match the new quantity while saving the project.
- D. A workflow can be triggered to inform the purchasing group.
Answer: C
NEW QUESTION 62
How can you grant individual authorization for WBS elements and networks?
- A. Activate access control lists (ACL) for the project profile and the network profile.
- B. Define a user status to lock the business transaction Update Project.
- C. Set the system status to "Lock Master Data".
- D. Activate access control lists (ACL) for the user master record.
Answer: A
NEW QUESTION 63
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
- A. Cost element reports can display costs but not revenues.
- B. The manual hierarchical revenue planning will be displayed only if expert mode is activated.
- C. The manual hierarchical revenue planning has no reference to cost elements.
- D. Cost element reports display integrated planning only.
Answer: C
NEW QUESTION 64
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.
- A. Approval of a service entry sheet
- B. Approval of a good receipt.
- C. Posting a goods receipt
- D. Creating a purchase order.
- E. Creating a service entry sheet
Answer: A,C
NEW QUESTION 65
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
- A. Availability control
- B. Cost forecast
- C. Easy Cost Planning
- D. Results analysis
Answer: A
NEW QUESTION 66
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Project simulations allow posting of actual data.
- B. Project simulations can be used to plan structures and costs.
- C. Project simulations can be created without using an operational project as a template.
- D. Project simulations can create purchase requisitions.
- E. Multiple project simulations can be used simultaneously.
Answer: B,C,E
NEW QUESTION 67
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
- A. The maintenance orders must be assigned as sub-networks.
- B. The maintenance orders must be assigned to WBS element.
- C. The maintenance order s must be assigned to the same budget profile as the project definition.
- D. The maintenance orders must be assigned to the same plant as the network.
Answer: D
NEW QUESTION 68
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter an offset of -18 days to the finish date of the activity.
- B. Enter February 10 as fixed date.
- C. Enter an offset of 10 days to the start date of the activity.
- D. Enter 10 days as duration.
Answer: B
NEW QUESTION 69
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
- A. Capacity load work center view
- B. Extended capacity evaluation
- C. Structure overview
- D. Individual overview capacity requirements
Answer: A
NEW QUESTION 70
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question
- A. The availability check for material components indicates missing parts
- B. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"
- C. The material master is set to external procurement
- D. The material is assigned to the activity as a non-stock material
Answer: B,D
NEW QUESTION 71
......